Split Case Water Pump Installation Preparation Guide: Foundation, Inspection and Setup
The installation of a split case water pump (single-stage double-suction centrifugal pump) is one of the most critical stages in the lifecycle of a pumping system. Proper pre-installation preparation ensures stable operation, high efficiency, and long service life.
A split case water pump is widely used in municipal water supply, industrial circulation systems, irrigation projects, and HVAC systems due to its large flow capacity, stable hydraulic performance, and convenient maintenance.

However, many operational problems originate from inadequate installation preparation rather than equipment defects. Issues such as poor foundation preparation, incomplete equipment inspection, or incorrect alignment planning may lead to vibration, seal leakage, or bearing failure.
This guide provides a systematic overview of preparation work required before installing a split case water pump, covering foundation inspection, equipment verification, tool preparation, and installation environment requirements.
1. Personnel, Planning, and Technical Preparation
Before installation begins, proper organizational and technical preparation must be completed.
| Preparation Category | Key Requirements |
| Installation supervision | Assign a qualified installation supervisor responsible for overall coordination |
| Technical personnel | Mechanical technicians and rigging operators must have appropriate certifications |
| Safety briefing | All personnel must receive safety and technical instructions before installation |
| Technical documents | Review pump drawings, technical specifications, installation manuals, and relevant standards |
| Installation plan | Prepare a lifting and installation plan for large or complex pump units |
| Documentation preparation | Prepare inspection records, measurement logs, and installation reports |
Thorough planning ensures the split case water pump installation process proceeds smoothly and safely.
2. Foundation Inspection and Preparation
The concrete foundation supports the static weight and dynamic load of the pump unit. Poor foundation conditions are one of the most common causes of vibration and misalignment.
Foundation Strength and Surface Condition
The foundation must reach at least 80% of its design strength before installation.
| Inspection Item | Requirements |
| Concrete strength | ≥80% of design strength |
| Surface condition | No cracks, honeycombing, or exposed reinforcement |
| Cleanliness | Surface must be free of oil, dust, and debris |
| Anchor bolt holes | Clean and free from standing water |
If the foundation was poured in winter conditions, curing conditions must be verified to ensure no freeze damage occurred.
Dimensional Verification
Precision instruments should be used to verify the foundation dimensions.
| Inspection Item | Allowable Deviation | Notes |
| Foundation elevation and centerline | ±5 mm | According to design drawings |
| Anchor bolt hole spacing | ≤ ±3 mm | Measured using vernier calipers |
| Verticality of bolt holes | ≤ 1 mm/m | Full-depth measurement |
| Foundation levelness | ≤2 mm per meter, ≤5 mm overall | Multiple measurement points |
Foundation Surface Treatment
| Treatment Item | Requirements |
| Surface roughening | Roughness depth ≥10 mm |
| Indentation density | 3–5 points per 100 cm² |
| Surface cleaning | Remove laitance, oil, dust |
| Shim contact area | ≥70% contact between shim and foundation |
Proper surface preparation ensures reliable bonding between the secondary grout layer and foundation.
Anchor Bolt Preparation
| Inspection Item | Requirements |
| Bolt size and length | Must match design drawings |
| Thread condition | No damage or corrosion |
| Bolt verticality | Installed vertically in reserved holes |
| Clearance at bottom | 10–20 mm space between bolt end and hole bottom |
Temporary supports should be used to prevent bolt displacement during secondary grouting.
3. Equipment Unpacking Inspection
Equipment inspection ensures that the delivered split case water pump meets technical specifications before installation.
Inspection should be conducted jointly by:
project owner
installation contractor
supervising engineer
equipment supplier
Equipment Inventory Verification
| Inspection Category | Items to Verify |
| Main equipment | Pump casing, motor, base frame |
| Rotating components | Shaft, impeller, bearings |
| Coupling components | Coupling hub, guard |
| Spare parts | Mechanical seals, gaskets, O-rings |
| Special tools | Impeller removal tools, bearing tools |
All inspection results should be recorded in an Equipment Unpacking Inspection Report.
Equipment Condition Inspection
| Inspection Category | Inspection Items | Requirements |
| External inspection | Pump casing, motor housing, flanges | No deformation or corrosion |
| Internal inspection | Impeller, shaft, casing interior | Required if transport distance >1000 km or storage >6 months |
| Rotor rotation test | Manual rotation | Rotor rotates smoothly for at least three revolutions |
| Motor inspection | Insulation resistance | ≥1 MΩ using megohmmeter |
Additional checks should confirm:
correct rotation direction marking
coupling guard installed
motor terminal box sealed and dry
4. Equipment Storage Requirements
If installation cannot proceed immediately, proper storage is necessary to prevent damage.
| Storage Item | Requirements |
| Pump openings | Seal with protective covers |
| Storage environment | Clean, dry, well-ventilated indoor area |
| Outdoor storage | Raise equipment ≥100 mm above ground |
| Weather protection | Waterproof and dustproof covering |
| Spare parts | Store separately with clear labeling |
Proper storage helps protect the internal surfaces of the pump casing and bearings.
5. Tools, Materials, and Site Preparation
Adequate preparation of tools and materials improves installation efficiency.
Tools and Measuring Instruments
| Tool Category | Specific Tools | Requirements |
| Lifting equipment | Crane, slings, shackles | Capacity ≥1.2× pump weight |
| Measuring instruments | Precision level, laser alignment system | Within calibration period |
| General tools | Wrenches, pry bars, hydraulic jacks | Complete tool sets |
| Special tools | Impeller puller, bearing puller | According to manufacturer |
Installation Materials
| Material Type | Items | Requirements |
| Shims | Flat and wedge shims | Carbon steel or stainless steel |
| Grouting material | Non-shrink grout | Strength ≥C40 |
| Lubrication materials | Lubricating oil | According to manufacturer |
| Auxiliary materials | Cleaning fluid, anti-corrosion grease | For cleaning and protection |
Installation Site Preparation
| Preparation Category | Requirements |
| Installation space | Adequate lifting and positioning area |
| Ground capacity | Ground must support crane load |
| Power supply | Reliable electrical supply with grounding |
| Safety equipment | Warning signs, fire extinguishers |
| Pipeline preparation | Pressure test at 1.5× design pressure |
Pipelines must be properly supported so that no external load is transmitted to the pump casing.
6. Additional Preparation for Large Pump Units
Large split case water pumps (≥10 tons) or pumps delivered in separate components require additional preparation.
| Preparation Task | Key Requirements |
| Trial assembly | Verify component fit before final installation |
| Rotor inspection | Rotor must rotate freely without abnormal noise |
| Surface cleaning | Clean all mating surfaces |
| Dimensional verification | Check tolerances before final assembly |
Pipeline and System Coordination
| Coordination Item | Requirements |
| Flexible connections | Install rubber expansion joints to reduce pipeline stress |
| Electrical installation | Follow motor manufacturer wiring specifications |
| Grounding system | Ensure reliable grounding protection |
| Final alignment | Perform after pipeline installation but before grouting |
Typical Alignment Tolerance
| Alignment Parameter | Allowable Value |
| Radial deviation | ≤0.05 mm |
| Angular deviation | ≤0.03 mm/m |
Split Case Water Pump Installation Checklist
| Inspection Item | Status |
| Foundation strength verified | □ |
| Foundation dimensions inspected | □ |
| Anchor bolts installed | □ |
| Equipment unpacking inspection completed | □ |
| Rotor rotation test completed | □ |
| Motor insulation resistance tested | □ |
| Installation tools prepared | □ |
| Pipeline cleaning completed | □ |
| Safety inspection completed | □ |
Common Installation Mistakes for Split Case Water Pumps
| Mistake | Possible Consequences |
| Installing pump before foundation strength is sufficient | Equipment vibration |
| Incorrect anchor bolt positioning | Base plate misalignment |
| Poor pump-motor alignment | Coupling wear and bearing damage |
| Pipeline stress transferred to pump | Pump casing deformation |
| Debris left inside pipelines | Impeller damage or blockage |
Avoiding these mistakes significantly improves long-term reliability and service life.
Conclusion
Proper preparation is essential for the successful installation of a split case water pump. Comprehensive planning, accurate foundation preparation, careful equipment inspection, and adequate installation tools all contribute to a smooth installation process.
By ensuring:
proper foundation conditions
complete equipment inspection
correct installation procedures
accurate alignment and system integration
engineers can guarantee safe, efficient, and long-term operation of split case water pump systems.
FAQ – for Split Case Pump
Learn about the key spare parts commonly used in split case pumps.
| Split Case Pump Spare Parts & Qty (2 Years) | ||||||||
| For Packing Seal Pump | ||||||||
| Spare Parts/Qty | Pump Qty (Including Spare Pump) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 8 | ≥10 | |
| Shaft Sleeve | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Bearing Collar | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Impeller Collar | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Packing Seal | 1 | 2 | 3 | 4 | 5 | 6 | 8 | 10 |
| O Ring | 1 | 2 | 3 | 4 | 5 | 6 | 8 | 10 |
| Shaft | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Impeller | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Wear Ring | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Packing Ring | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Packing Gland | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Bearing | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| For Mechanical Seal Pump | ||||||||
| Spare Parts/Qty | Pump Qty (Including Spare Pump) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 8 | ≥10 | |
| Shaft Sleeve | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Bearing Collar | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Impeller Collar | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Mechanical Seal | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| O Ring | 1 | 2 | 3 | 4 | 5 | 6 | 8 | 10 |
| Shaft | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Impeller | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Wear Ring | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
| Mechanical Gland | 0 | 0 | 0 | 1 | 1 | 1 | 2 | 3 |
| Bearing | 1 | 1 | 1 | 2 | 2 | 3 | 4 | 5 |
Discover how to select the right split case pump materials based on fluid properties and operating conditions.
| Pump Parts | For Clear Water | For Sewage | For Seawater |
| Casing | Cast Iron | Ductile Iron | S.S / Super Dulex |
| Impeller | Cast Iron | Cast Steel | S.S / Super Dulex / Tin Bronze |
| Shaft | Steel | Steel | S.S / Super Dulex |
| Shaft Sleeve | Steel | Steel | S.S / Super Dulex |
| Wear Ring | Cast Iron | Cast Steel | S.S / Super Dulex / Tin Bronze |
| Remark | Final material depends on the liquid condition or the client’s request. | ||
Follow the essential installation steps to ensure safe and reliable operation of the split case pump.
| Standardized Installation Procedure for Split Case Pump | |||
| Work Stage | No. | Main Steps | Key Operations & Notes |
| I. Pre-Installation Preparation | 1 | Site & Foundation Inspection | • Clean the installation site and ensure sufficient space for operation and lifting. • Check the concrete foundation strength, dimensions, elevation, and anchor bolt positions according to drawings. The foundation surface should be flat and free of oil. |
| 2 | Equipment Unpacking & Inspection | • Verify that the pump, motor, and accessories match the contract specifications. • Inspect the equipment for any transportation damage and ensure all parts are complete. • Check that all accompanying documents (drawings, manuals, certificates) are complete. | |
| 3 | Tools & Material Preparation | • Prepare lifting equipment (hoist, sling), shims, level, dial indicator, wrenches, feeler gauge, lubricants, sealant, etc. • Prepare cleaning agents and cloths for cleaning mating surfaces. | |
| II. Pump Body Installation | 4 | Lifting & Positioning | • Lift the pump using the lifting holes or lugs; never lift by the pump shaft or inlet/outlet pipes. • Place the pump on the foundation, insert anchor bolts into base holes, do not tighten yet. |
| 5 | Initial Leveling & Alignment | • Place a level on the pump’s inlet/outlet flange or machined surface, adjust shims to roughly level the pump (tolerance ≤0.1 mm/m). • Use the pump shaft centerline as a reference to preliminarily align the pump. | |
| 6 | Primary Grouting | • Pour high-strength non-shrink grout into the anchor bolt holes; the grout layer should be dense and slightly below the foundation surface. • Curing: wait until the grout is fully cured (usually 3–7 days) before fine adjustment and tightening. | |
| 7 | Final Leveling & Alignment | • After grout curing, tighten anchor bolts. • Recheck pump level with a precision level. • Motor installation & alignment: lift the motor in place, use a dial indicator or laser alignment device, align the motor to ensure pump and motor shafts are coaxial (radial & axial deviation ≤0.05 mm). Tighten motor anchor bolts after alignment. | |
| III. Piping & Accessories Installation | 8 | Piping Connection | • Principle: never force pipe connections using the pump flanges to avoid stress on the pump body. • Piping should be independently supported, ensure natural alignment without stress. • It is recommended to install expansion joints near the pump inlet/outlet to absorb thermal expansion/contraction and installation errors. |
| 9 | Seals & Cooling System | • For mechanical seals, connect flushing/cooling piping, ensure smooth flow, flushing pressure 0.05–0.15 MPa higher than seal chamber. • For packing seals, install packing and adjust gland tightness (do not overtighten initially). | |
| 10 | Lubrication & Instruments | • Add specified grade and quantity of lubricant to bearing housing to oil mark midline. • Install pressure gauge, thermometer, etc.; pressure gauge should be between pump outlet and first valve. | |
| IV. Post-Installation Checks & Test Run | 11 | Final Checks | • Manual rotation: rotate coupling, ensure rotor turns smoothly, no friction or binding. • Check all bolts are tightened and guards are in place. • Jog motor: confirm rotation direction matches pump casing arrow. |
| 12 | Priming & Test Run | • Open inlet valve, fill pump with conveyed medium, completely expel air. • Close outlet valve, start motor. • Slowly open outlet valve to desired condition, check pressure, flow, vibration, noise, bearing temperature (≤80 ℃), and seal leakage. Test run ≥2 hours. | |
Explore proper disassembly and maintenance procedures to maximize the split case pump service life.
| Standardized Disassembly & Maintenance Procedure for Split Case Pump | |||
| Work Stage | No. | Main Steps | Key Operations & Notes |
| I. Pre-Disassembly Preparation | 1 | Shutdown & Isolation | • Safety first: slowly close the outlet valve, cut off power, and apply lockout/tagout (LOTO). • Close the inlet valve, open the pump vent and drain valves, completely drain the medium. For toxic or hazardous media, perform purging and verify safe conditions. |
| 2 | Disconnect External Connections | • Remove coupling guard and connecting bolts. • Disconnect all pipes, instrumentation lines, and cooling/seal water lines if the pump will be lifted as a whole. Seal open ends to prevent foreign object entry. | |
| 3 | Tools & Preparation | • Prepare pullers, hydraulic wrenches, copper bars, lifting equipment, and various wrenches. • Prepare parts boxes and labels to organize and mark removed bolts and small parts for easier reassembly. | |
| II. Pump Body Disassembly | 4 | Remove Accessories | • Remove pressure gauges, thermometers, and other instruments. • Open bearing housing oil drain and collect used lubricant. |
| 5 | Remove Coupling & Bearing End Covers | • Use a puller to smoothly remove the half-coupling from the pump shaft; avoid hammering. • Remove bearing end covers and gland bolts in sequence, then remove the covers. | |
| 6 | Lift Out Rotor Assembly | • Remove bearing housing bolts on both sides of the pump and horizontally lift the entire rotor assembly (shaft, impeller, bearings, sleeves) smoothly. Avoid collisions. | |
| 7 | Disassemble Split Case Pump Body | • Loosen and remove pump casing bolts in a diagonal sequence. • Lift the pump casing carefully and place on a padded or wooden platform. Protect the split case mating surface—avoid dents or scratches. | |
| 8 | Remove Internal Components | • Before disassembly, measure and record key clearances (e.g., impeller to wear ring, bearing clearance). • Use special wrenches to remove impeller locknut, then remove impeller. Remove shaft sleeve, mechanical seal or packing housing sequentially. | |
| III. Inspection, Maintenance & Reassembly | 9 | Parts Cleaning, Inspection & Measurement | • Clean all parts thoroughly, inspect for wear, corrosion, cracks. Focus on: – Impeller: cavitation, wear, dynamic balance. – Wear ring/seal ring: measure wear gap; replace if exceeding limits (typically >1.5× original gap). – Pump shaft: check straightness (total runout ≤0.05 mm). – Bearings: check clearance, rolling surface for pitting or spalling. – Mechanical seals: check stationary/rotating faces and spring elasticity. • Decide whether to repair or replace parts. |
| 10 | Reassembly (Reverse Order of Disassembly) | • Core principle: clean, align, and tighten evenly. • Replace all seals (O-rings, gaskets). Apply a thin layer of sealant (e.g., anaerobic) on split case mating surfaces. • Lift pump casing, tighten bolts diagonally in stages to manufacturer torque. • Reinstall rotor assembly, adjust impeller axial clearance to manufacturer spec. • Install bearings and adjust bearing clearance. • Reinstall coupling and perform precise pump-to-motor alignment (same as installation standard). | |
| 11 | Final Verification | • Manually rotate to ensure smooth, unrestricted motion. • Connect piping, add new lubricant to specified level. • Conduct final verification according to installation procedure “Priming & Test Run” to ensure normal operation parameters. | |
Find practical solutions to the most common split case pump operating issues.
| Split Case Pump Common Faults and Solutions | ||
| Problem | Causes | Solutions |
| 1. Pump not priming / Cannot discharge liquid | 1. Suction pipe, suction valve, foot valve not primed; air ingress. 2. Pump casing or suction pipe contains trapped air. 3. Motor rotation reversed. 4. Suction inlet leakage or failure. 5. Suction lift exceeds allowable maximum. | 1. Prime suction line and foot valve; eliminate air leaks. 2. Vent casing & suction line. 3. Correct motor wiring/rotation. 4. Repair suction inlet. 5. Reduce suction lift or add booster. |
| 2. Flow insufficient / Small discharge | 1. Inlet valve closed or partially closed; suction screen blocked. 2. Impeller blockage, foreign objects. 3. Wear at suction port (seal ring), impeller or casing wear. 4. Suction line contains air. 5. Pump speed too low. | 1. Fully open inlet valve; clean filter/screen. 2. Remove blockage/clean impeller. 3. Repair/replace worn components. 4. Purge air from suction. 5. Restore correct operating speed. |
| 3. Low head / Insufficient pressure | 1. Impeller clearance too large or impeller damage. 2. Low rotation speed. 3. Cavitation. 4. Suction pipe diameter too small. 5. Discharge head exceeds pump capacity. | 1. Adjust or replace impeller. 2. Increase speed within rating. 3. Improve suction conditions or reduce NPSH. 4. Increase suction pipe size. 5. Reduce discharge head. |
| 4. Excessive vibration / Abnormal noise | 1. Shaft misalignment. 2. Bearing damage. 3. Loose motor mounting. 4. Coupling or impeller imbalance. 5. Motor vibration. 6. Base/frame loose. 7. Improper pipe support causing resonance. | 1. Re‑align pump & motor. 2. Replace bearings. 3. Secure motor base. 4. Correct balance; inspect coupling. 5. Reduce motor vibration. 6. Tighten base. 7. Add pipe supports. |
| 5. Bearing overheating | 1. Improper lubrication (insufficient, wrong type, contaminated). 2. Bearing damage. 3. Poor alignment. 4. Bearing housing misfit. 5. Insufficient cooling. 6. Excessive rotational speed. | 1. Re‑lubricate with correct grease/oil. 2. Replace bearings. 3. Realign pump & motor. 4. Adjust housing fit. 5. Improve ventilation/cooling. 6. Operate within speed rating. |
| 6. Mechanical seal leakage | • Seal faces worn, uneven, O‑ring aging, spring failure. • Packing not lubricated or tightened. | • Replace mechanical seal and O‑rings; inspect shaft finish. • Adjust packing gland; ensure correct packing and tension. |
| 7. Motor overload / Tripped protection | 1. Insufficient power supply. 2. Phase loss / Power imbalance / Poor wiring. 3. Excessive load (impeller blockage), pump stalled. 4. Excessive starting current. 5. Motor overheating. 6. Short‑circuit or earth fault. | 1. Restore proper supply voltage. 2. Check wiring and phases; correct imbalance. 3. Remove blockage; clear shaft rotation. 4. Use soft start or reduced voltage starter. 5. Improve cooling. 6. Find & repair electrical fault. |
| 8. Cannot start or slow start | 1. Power supply abnormal (voltage drop). 2. Starter contactor open. 3. Motor winding open circuit. 4. Control circuit faulty. | 1. Check power and restart. 2. Check and replace contactor. 3. Repair/replacement of winding. 4. Correct control wiring. |
| 9. Pump vibration increases at no load | 1. Rotor imbalance, bent shaft. 2. Loose rotating parts. 3. Coupling looseness. 4. Pump suction/delivery line back‑pressure issue. | 1. Balance rotor or repair shaft. 2. Tighten rotating assembly. 3. Tighten coupling. 4. Eliminate back‑pressure and correct piping. |
| 10. Efficiency drop / Performance deterioration | 1. Wear of impeller & casing. 2. Internal passage clogging, scale/slag. 3. Air entrainment in suction. 4. Operating point far from BEP. | 1. Replace worn parts. 2. Clean flow passages; flush. 3. Eliminate suction air leaks. 4. Adjust operating conditions toward BEP. |
Learn the maintenance practices that help improve split case pump reliability and reduce downtime.
| Daily Maintenance and Care for Split Case Pumps | ||
| Maintenance Category | Maintenance Item | Details & Standards |
| I. Pre‑Operation Inspection | 1. Visual & Connection Check | • Check the pump casing, motor, coupling, etc., for cracks, deformation or damage. • Check all connection fasteners (especially pump‑to‑base and base bolts) for tightness to prevent leakage or vibration. • Check piping and joint areas for looseness. |
| 2. Lubrication Inspection | • Oil lubrication: Check if the oil level in the oil chamber is at the center mark; whether the oil is clean. Replace promptly if oil is turbid or contains impurities. • Grease lubrication: Check if the grease is sufficient and clean. Note: Water‑based bearings use grease X; motors use grease Y — the two must not be mixed. | |
| 3. Turn Shaft & Rotation Confirmation | • Manually rotate the coupling to check if the pump shaft rotates freely with no friction noise. • Start motor briefly to confirm the rotation direction is consistent with the direction indicated by the pump arrow. | |
| 4. Seal & Suction Check | • Check the mechanical seal and packing seal condition. • Open pump suction valve and drain water until the casing is full, then vent air (no dry running). | |
| II. Monitoring During Operation | 1. Parameter Monitoring | • Pressure & Flow: Monitor inlet and outlet pressures and flow to ensure operation within the rated range for optimum efficiency. • Bearing Temperature: Bearing temperatures should remain between 40–60 °C, and the motor temperature should not exceed 80 °C. If overheated, check lubrication and cooling systems. |
| 2. Vibration & Noise | • Listen to running noise: should be smooth hum. If there are abnormal noises, impacts, etc., stop and inspect immediately. • Observe vibration condition; abnormal vibration may indicate imbalance, bent shaft, uneven wear, or cavitation. | |
| 3. Seal & Leakage Monitoring | • Mechanical seal: Normal leakage rate should not exceed 5 drops per minute. • Packing seal: Through adjustment tighten, leakage rate should be controlled at about 10‑15 drops/min (approx. 30 ml/min) depending on packing size. Adjust to desired leakage. | |
| 4. Instruments & Motor | • Check all instruments (pressure gauge, temperature gauge, etc.) for normal readings. • Check motor current and electrical system; no abnormal heating. | |
| III. Periodic (Planned) Maintenance | 1. Lubrication Management | • Oil lubrication: Change first after 100 operating hours, then every 500 hours. • Grease lubrication: Generally replenish or change every 3 months; follow manufacturer service schedule. |
| 2. Seal System Maintenance | • Packing seal: Replace packing rings as needed; ensure stuffing box is properly tightened and align packing ring gaps at 90°–120°. • Mechanical seal: Check flushing liquid pressure; it should be 0.05–0.1 MPa. Replace seal if excessive wear or leakage. | |
| 3. Bearing & Coupling Check | • Monthly manually check coupling and shaft for smooth rotation, no abnormal noise. • Periodically check bearing housing for dirt, wear and proper lubrication. | |
| 4. Impeller & Flow Passage Cleaning | • Every 3 months or based on water quality, check impeller for buildup, corrosion, wear; clean off sediment, debris.• Check impeller clearance; if gap is too large (e.g., >0.1 mm), replace as required. | |
| 5. Alignment & Tightening | • Periodically check alignment between pump and motor; allowable deviation ≤0.05 mm. • Retighten base bolts and major fasteners as needed. | |
| IV. Shutdown & Long‑Term Stop | 1. Normal Shutdown | • Procedure: close outlet valve first → power off → close inlet valve and pressure gauge valves. |
| 2. Winter Anti‑Freeze | • When ambient temperature is ≤ 0 °C, after shutdown drain water from pump body, and ensure piping is drained to prevent freezing. | |
| 3. Long‑Term Storage | • Drain all internal water and clean thoroughly. • Apply rust preventive oil (shaft, impeller, contact areas), reinstall and protect for storage. | |
| V. Cleaning & Record Keeping | 1. Equipment Cleaning | • Weekly wipe pump body, motor, and base surfaces; especially clean motor cooling fins. • Regularly clean around instrument panels to prevent dust accumulation. |
| 2. Operation Records | • Establish and maintain operation & maintenance logs including operating hours, pressures, temperature, vibration, lubrication replacement time, fault handling, etc., to facilitate equipment condition tracking and planned maintenance. | |







